Electricity distribution is the penultimate stage in the delivery (before retail) of electricity to end users. It is generally considered to include medium-voltage (less than 50 kV) power lines, electrical substations and pole-mounted transformers, low-voltage (less than 1000 V) distribution wiring and sometimes electricity meters.
Introduction of alternating current
The adoption of alternating current (AC) for electricity generation following the War of Currents dramatically changed the situation. Power transformers, installed at power stations, could be used to raise the voltage from the generators, and transformers at local substations reduced it to supply loads. Increasing the voltage reduced the current in the transmission and distribution lines and hence the size of conductors required and distribution losses incurred. This made it more economical to distribute power over long distances. Generators (such as hydroelectric sites) could be located far from the loads.
In North America, early distribution systems used a voltage of 2200 volts corner-grounded delta. Over time, this was gradually increased to 2400 volts. As cities grew, most 2400 volt systems were upgraded to 2400/4160 volt, three-phase systems. In three phase networks that permit connections between phase and neutral, both the phase-to-phase voltage (4160, in this example) and the phase-to-neutral voltage are given; if only one value is shown, the network does not serve single-phase loads connected phase-to-neutral. Some city and suburban distribution systems continue to use this range of voltages, but most have been converted to 7200/12470Y, 7620/13200Y, 14400/24940Y, and 19920/34500Y.
European systems used 3300 volts to ground, in support of the 220/380Y volt power systems used in those countries. In the UK, urban systems progressed to 6.6 kV and then 11 kV (phase to phase), the most common distribution voltage.
Distribution network configurations
Distribution networks are typically of two types, radial or interconnected (see Spot Network Substations). A radial network leaves the station and passes through the network area with no normal connection to any other supply. This is typical of long rural lines with isolated load areas. An interconnected network is generally found in more urban areas and will have multiple connections to other points of supply.
These points of connection are normally open but allow various configurations by the operating utility by closing and opening switches. Operation of these switches may be by remote control from a control centre or by a lineman. The benefit of the interconnected model is that in the event of a fault or required maintenance a small area of network can be isolated and the remainder kept on supply.
Within these networks there may be a mix of overhead line construction utilizing traditional utility poles and wires and, increasingly, underground construction with cables and indoor or cabinet substations. However, underground distribution is significantly more expensive than overhead construction. In part to reduce this cost, underground power lines are sometimes co-located with other utility lines in what are called Common utility ducts. Distribution feeders emanating from a substation are generally controlled by a circuit breaker which will open when a fault is detected. Automatic Circuit Reclosers may be installed to further segregate the feeder thus minimising the impact of faults.
Long feeders experience voltage drop requiring capacitors or voltage regulators to be installed.
Variables include:
- AC or DC – Virtually all public electricity supplies are AC today. Users of large amounts of DC power such as some electric railways, telephone exchanges and industrial processes such as aluminium smelting either operate their own or have adjacent dedicated generating equipment, or use rectifiers to derive DC from the public AC supply
- Voltage, including tolerance (usually +10 or -15 percentage)
- Frequency, commonly 50 & 60 Hz, 16-2/3 Hz for some railways and, in a few older industrial and mining locations, 25 Hz
- Phase configuration (single phase, polyphase including two phase and three phase)
- Maximum demand (usually measured as the largest amount of power delivered within a 15 or 30 minute period during a billing period)
- Load Factor, expressed as a ratio of average load to peak load over a period of time. Load factor indicates the degree of effective utilization of equipment (and capital investment) of distribution line or system.
- Power factor of connected load
- Earthing arrangements – TT, TN-S, TN-C-S or TN-C
- Maximum prospective short circuit current
- Maximum level and frequency of occurrence of transients
Modern distribution systems
The modern distribution system begins as the primary circuit leaves the sub-station and ends as the secondary service enters the customer’s meter socket. A variety of methods, materials, and equipment are used among the various utility companies across the U.S., but the end result is similar. First, the energy leaves the sub-station in a primary circuit, usually with all three phases.
The most common type of primary is known as a wye configuration (so named because of the shape of a “Y”.) The wye configuration includes 3 phases (represented by the three outer parts of the “Y”) and a neutral (represented by the center of the “Y”.) The neutral is grounded both at the substation and at every power pole. In a typical 12470Y/7200 volt system, the pole mount transformer’s primary winding is rated for 7200 volts and is connected across one phase of power and the neutral. The primary and secondary (low voltage) neutrals are bonded (connected) together to provide a path to blow the primary fuse if any fault occurs that allows primary voltage to enter the secondary lines. An example of this type of fault would be a primary phase falling across the secondary lines. Another example would be some type of fault in the transformer itself.
The other type of primary configuration is known as delta. This method is older and less common. Delta is so named because of the shape of the Greek letter delta, a triangle. Delta has only 3 phases and no neutral. In delta there is only a single voltage, between two phases (phase to phase), while in wye there are two voltages, between two phases and between a phase and neutral (phase to neutral). Wye primary is safer because if one phase becomes grounded, that is, makes connection to the ground through a person, tree, or other object, it should trip out the fused cutout similar to a household circuit breaker tripping. In delta, if a phase makes connection to ground it will continue to function normally. It takes two or three phases to make connection to ground before the fused cutouts will open the circuit. The voltage for this configuration is usually 4800 volts. Transformers are sometimes used to step down from 7200 or 7600 volts to 4800 volts or to step up from 4800 volts to 7200 or 7600 volts. When the voltage is stepped up, a neutral is created by bonding one leg of the 7200/7600 side to ground. This is commonly used to power single phase underground services or whole housing developments that are built in 4800 volt delta distribution areas. Step downs are used in areas that have been upgraded to a 7200/12500Y or 7600/13200Y and the power company chooses to leave a section as a 4800 volt setup. Sometimes power companies choose to leave sections of a distribution grid as 4800 volts because this setup is less likely to trip fuses or reclosers in heavily wooded areas where trees come into contact with lines.
Electrical power










May 20, 2009 at 2:38 pm
Great info=) Hope to come back again soon..
June 29, 2009 at 1:09 pm
Thanks a million…really enlightened by the info…i’m from a computer science background so it was really helpful for me as part of my research into what distribution lines are about: Muchas Gracias.